Strength and leak-tightness tests of the reactor building’s leak-tight containment shell have been successfully completed at Unit 1 of the Akkuyu Nuclear Power Plant in Mersin. According to Akkuyu Nuclear JSC, the tests were conducted continuously for eight days, during which the air pressure inside the containment shell was gradually raised to 0.46 MPa.
This value was 15 percent above the 0.4 MPa design pressure used to assess the structure’s leak-tightness. At the highest pressure, the force exerted on each square meter of the containment shell was equivalent to the weight of approximately 47 tonnes.
“We successfully tested the main protective barrier”
Experts monitored stresses in the structure and deformations under load throughout all stages of the test. The company said the results confirmed that the structure met design requirements and could withstand internal pressure above atmospheric pressure. Akkuyu Nuclear General Manager Sergei Butckikh said equipment, structures and safety systems at Unit 1 were being tested in stages, adding, “We successfully tested the unit’s main protective barrier.”

The first reactor of the Rosatom-built plant is scheduled to begin operating this year.
Invitation to experts from Kazakhstan
Akkuyu is also drawing attention for the foreign experts involved in its construction. On November 12, Almasadam Satkaliyev, head of Kazakhstan’s Atomic Energy Agency, met with Kazakh experts working on the Akkuyu construction project and invited them to work on nuclear projects in Kazakhstan. Satkaliyev said, “Any experience is valuable, both in construction and operation. If you would like to use your knowledge and experience in Kazakhstan, we would be pleased to welcome you.”
Kazakhstan plans to build at least three nuclear power plants.